Designed to fit the contours of the site, this building will house an eye clinic, including a laser eye correction theatre. The exterior has bands of contrasting brick and a series of pitched zinc clad roofs. The significant steelwork structure is designed to create large internal spaces which are then subdivided to create the facilities needed for the clinic. The services are extensive.

Architect: Toh Shimazaki Architecture
Quantity Surveyors: Bonfield
Structural Engineer: Fluid
Services Engineer: Max Fordham
Week 1

Week 1

The architect model.

Week 4

Week 4

The rock substrate has been reduced in level and foundation strips excavated. Due to the rock strata, shuttering was needed.

Week 5

Week 5

The foundations are poured to north half of the building and the drains are set out.

Week 6

Week 6

Having installed the drains and laid oversite concrete, the first layer of damp proof membrane is laid.

Week 8

Week 8

The slab reinforcement is complete and the retaining wall and column reinforcement is well advanced.

Week 10

Week 10

Half of the concrete slab has been poured together with the kickers for the retaining wall and the columns.

Week 14

Week 14

Most of the retaining wall has been poured and the reinforcement prepared for the first of six columns.

Week 16

Week 16

The first of the six columns supporting the first floor in situ slab is poured.

Week 17

Week 17

Blockwork commenced after the first windposts have been installed.

Week 17

Week 17

All six columns supporting the fist floor slab are poured.

Week 17

Week 17

The foundations for the south section of the building are poured.

Week 18

Week 18

Having incorporated the windposts in the inner skin blockwork, the face brickwork commenced.

Week 20

Week 20

The final section of the slab is poured enabling the final ground floor windposts to be installed.

Week 23

Week 23

The first floor steels for the north section of the building are fitted enabling the joists to be installed. The first flor slab shows in the foreground.

Week 25

Week 25

The final windposts on the first floor are fitted. Note the complexity of the setting out due to changes in floor level and roof pitch.

Week 25

Week 25

The timber trusses for the south roof are lifted into position, each being different due to the trigonometry of the roof.

Week 26

Week 26

The first rafters are pitched to the shallow section of the south end of the roof.

Click on an image to view it.